Siena Towers – AS OF MAY 2025
Siena Towers
Tower Two is 83% complete.
Construction Details:
– Ongoing landscaping works on the 5TH Floor
– Ongoing painting, ceiling, and framing works for the Amenity Lounge Room, Function Room, and Day Care Room on the 5TH Floor
– Completed residential units on the 6TH to 11TH Floor
– Ongoing finishing works on the 12TH to 15TH Floor
– Ongoing Mechanical, Electrical, Plumbing, Fire, and Safety (MEPFS) functionality test on the 16TH to 18TH Floor
– Ongoing painting works and installation of plumbing fixtures on the 17TH to 21ST Floor Ongoing installation of toilet and floor tiles on the 22ND Floor
License to sell:
HLURB LS NO.:
Project Location: Loyola Ave., cor Marquinton Drive, Brgy. Sto. Nino, Marikina City
Developer: Horizon Land Development Corp.
Owner: Horizon Land Development Corp.
Completion Date: December 31, 2025
Head of Corporate Communications
Gizelle is a marketing and communications professional with extensive experience in the real estate industry, specializing in brand strategy, marketing communications, corporate communications, and integrated campaigns. She has built her career working across brand development, strategic communications, public relations, systems development, and marketing, with experience spanning both corporate and consumer-facing initiatives.
At Federal Land, Gizelle leads the Corporate Communications Department handling the company’s diverse portfolio, helping shape the narratives and experiences behind some of its most notable developments.
linkedinExplore Our Latest News & Events
MARCO POLO PARKPLACE – AS OF June 30 2025
HARTWOOD VILLAGE – AS OF MAY 2025
MARCO POLO PARKPLACE – AS OF April 30 2025